Marking jobs as complete

Change job status to completed

Danna avatar
Written by Danna
Updated over a week ago

FAQ: How do I mark a job complete?

No need for that. Simply activate the next job and Matics will automatically mark the previous job complete (Status 20), granted it has reached its production target.

If it hasn't reached its target, it will be automatically suspended instead. In this case you'll need to manually change its status to Status 20 - completed via

Jobs > Terminate Jobs.

Where the Terminate Jobs option is found on the main menu

Related articles

Personalize tables (for information on filtering and sorting tables

Did this answer your question?