Why use it?

This component presents as a heat-map ('load') infographic information about the utilization efficiency of the department's machines per hour. The Availability PE value is based on the following calculation:

Availability PE = actual production time / planned production time

When using this component to compare between independent machines, you can easily pinpoint machines with problematic performance and the hour in which this occurred.

example of Availability PE Per Hour - By Machine infographic

The Total row indicates the availability of the machine for the selected period, based on the active time of JoSh's run on the machine (weighted average).